Project Status:
Phase 2: Design & Tendering
Project Scope:
Design and construction of a new single-basin indoor aquatics facility within the $30M budget
Project Objectives:
- To deliver a new single-basin aquatic facility within the approved $30,000,000 budget
- Include the program features identified in the Feasibility Study
- Ensure full accessibility for all community members
- Keep the existing outdoor pool operational during all construction seasons and beyond
- Meet the schedule established through the detailed project plan
Why now?
The Harry Church Indoor Pool, also knows as the Weyburn Leisure Centre, was unable to open for the 2024/2025 Winter season due to significant degradation of the pool basin occurring below the tiled surface. The pool basin, hot tub and pool deck concrete structures have all deteriorated 10-15 years prior to their expected lifecycle.
Latest News
June 22, 2026
Colliers Project Leaders presented their findings from the evaluation and recommendation on the Prime Consultant RFP. Council awarded the project to P3Architecture Partnership (P3A) and approved the Steering Committee to proceed with contract negotiations with the preferred proponent, with a budget allocation of $1,860,652.50 (including PST).
Contract review and finalization period is expected to take approximately two weeks and will include incorporation of negotiated terms, confirmation of scope alignment and completion of the legal review.
The Prime Consultant Kick-Off Meeting is set for June 26, 2026. The kick off will formally initiate Prime Consultant services, confirm communication protocols, review project milestones and establish expectations for design development, stakeholder emgagement and reporting requirements.
Following the Kick-Off Meeting, P3A will begin Prime Consultant services in accordance with the finalized contract and established project schedule.
Project Timeline
- Schematic and Detailed Design: Fall 2027
- Contract Documents & Tendering: by Spring 2028
- Construction & Post Construction: by September 2029
- Grand Opening: by Spring 2030
High Level Project Timeline with Detailed Phase Activities
February 1 – April 1, 2026 (≈ 2 months)
Set the foundation and governance for project success
Key Activities:
- Establish formal Project Governance Structure
- Define roles, decision authority, escalation paths, and Council reporting
- Confirm Steering Committee and working group membership
- Develop and approve the Project Charter
- Confirm project objectives, success criteria, constraints, assumptions, and risks
- Align expectations across Council, Administration, and key stakeholders
- Prepare the Project Management Plan
- Define scope control, cost control, schedule management, risk and change management processes
- Facilitate a Project Planning Workshop
- Bring City departments, stakeholders, and advisors together to align on priorities
- Confirm delivery methodology
- Evaluate Design‑Bid‑Build, Design‑Build, Construction Management options
- Recommend approach best aligned with cost, schedule, risk, and City capacity
- Develop a high‑level procurement and engagement strategy
- Design team procurement approach
- Stakeholder and user engagement framework
Key Outcomes:
- Clear governance and accountability
- Approved project roadmap
- Agreed‑upon budget framework, schedule targets, and risk strategy
April 1, 2026 – August 1, 2027 (≈ 16 months)
Design the facility, control costs, and select construction partners
Key Activities:
- Procure and manage the design consultant team
- Architectural, engineering, cost, and specialty consultants
- Manage design progression through defined milestones
- Concept and schematic design
- Design development
- Construction‑ready documents
- Lead structured design review workshops
- Confirm alignment with program needs, accessibility, operations, and maintenance
- Identify cost drivers and value‑engineering opportunities
- Maintain budget alignment
- Continuous cost estimating and reconciliation with the project budget
- Adjust scope or design early to avoid later overruns
- Coordinate stakeholder and user input
- City operations staff, aquatics staff, accessibility stakeholders
- Prepare and manage contractor pre‑qualification
- Ensure only capable, experienced builders are invited to bid
- Administer tendering and evaluation process
- Review submissions for compliance, pricing, and value
- Recommend preferred contractor for award
- Finalize contract terms, schedules, and risk allocation
Key Outcomes:
- Fully coordinated, buildable design
- Construction partner selected through a fair and transparent process
- Confirmed construction budget and baseline schedule
August 1, 2027 – July 31, 2029 (≈ 24 months)
Deliver the facility safely, on time, and within budget
Key Activities:
- Mobilization and site setup oversight
- Review contractor logistics, safety, and staging plans
- Chair regular construction and project team meetings
- Track progress, issues, and decisions
- Monitor schedule, cost, and quality performance
- Site inspections and progress verification
- Ongoing cost tracking and forecasting
- Administer change management
- Evaluate scope changes, pricing, and schedule impacts
- Support City decision‑making on changes
- Oversee quality assurance and control
- Confirm work complies with drawings, specifications, and codes
- Coordinate inspections and approvals
- Liaise with authorities having jurisdiction
- Certify contractor progress payments
- Ensure payments align with verified progress
- Provide regular reporting to City Administration and Council
- Budget status, schedule status, risks, and key issues
Key Outcomes:
- Construction completed to required quality standards
- Costs and schedule actively controlled
- Issues resolved early to avoid delays or cost escalation
August 1 – September 1, 2029 (≈ 1 month, plus warranty period)
Transition from construction to operations
Key Activities:
- Manage deficiency identification and correction
- Track and close deficiencies before opening
- Oversee system commissioning
- Pool systems, mechanical, electrical, and life‑safety systems
- Coordinate staff training and operational readiness
- Facility systems, maintenance protocols, and safety procedures
- Support facility turnover
- Manuals, warranties, as‑built drawings, and documentation
- Finalize financial close‑out
- Release holdbacks, close contracts, finalize funding claims
- Monitor warranty issues post‑opening
Key Outcomes:
- Fully operational, tested, and commissioned facility
- Smooth transition to City operations staff
- Reduced post‑opening disruptions
Project Documents
Dive Deeper
FAQ’s
Option #1: Renovation within existing facility envelope
• Estimated Cost: $24,671,875.00
o Maintain the current building envelope
o Leisure pool with zero beach entry (no competitive 25m tank)
Option #2: New facility construction, 1 tank
• Estimated Cost: $30,093,750.00
o Demolition of existing building and construction of new facility.
o Sunroom remains but converted to pavilion
o Competitive 25m pool with zero beach entry
Option #3: Renovation and expansion of existing facility envelope
• Estimated Cost: $32,375,000.00
o Maintain portion of current building envelope with new addition
o 2 separate pool basins:
– leisure pool with zero beach entry
– competitive 25m pool with diving board
Option #4: New facility construction, 2 tanks
• Estimated Cost: $45,843,750.00
o Demolition of existing building and construction of new facility.
o Sunroom remains but converted to pavilion
o 2 separate pool basins:
– Leisure pool with zero beach entry
– Competitive 25m pool with diving board
All four options have increased changing room sizes with gender neutral and universal options. Amenities such as hot tub, sauna, steam room, cold plunge, and waterslide have been included in each option. Increased viewing areas with temporary seating are also included in each option.
Where facility demolition is proposed there is potential for renovating the interior of the facility to utilize the space for a different purpose. However, costs associated with renovating to repurpose the facility have not yet been determined and would require further study. Demolition costs of $1,125,000 are included in options 2 & 4.
Operational Cost Forecasts
In addition to the capital construction costs, the City will also incur ongoing operational investment requirements associated with the annual operations of the facility. As the City operated the indoor pool in the past, some of these ongoing impacts are already accounted for in City budgets however there will be an operational cost impact of a new or renovated facility. It is important to note that these estimates should be considered 2025 values and have been derived from 2023 actual observed revenues and expenses at the Weyburn Leisure Centre.
2023 Actual
- Revenues: $ 324,445.00
- Exepenses: $1,243,034.00
- Net Operations: ($918,588.00)
- Cost Recovery: 26.10%
Estimate Option #1
- Revenues: $445,939
- Exepenses: $1,355,106
- Net Operations:($909,167)
- Cost Recovery: 32.91%
Estimate Option #2
- Revenues: $474,429
- Exepenses: $1,438,997
- Net Operations:($964,568)
- Cost Recovery: 32.97%
Estimate Option #3
- Revenues: $645,167
- Exepenses: $1,953,440
- Net Operations:($1,308,273)
- Cost Recovery: 33.03%
Estimate Option #4
- Revenues: $645,167
- Exepenses: $2,251,301
- Net Operations:($1,606,134)
- Cost Recovery: 28.66%
These are the Water Polo Events held each year (taken from the Water Polo Saskatchewan website):
- Community League: 6 x 1 day events in Winter (Weyburn annually hosted one event in January)
- Provincial: 1 in the Winter, 1 in the Spring, 1 in the Summer – each are 2-day events
- Provincial Evolution League: 2 events, 3 days each
- Nationals: 16 events across Canada, 2 of which are held in Saskatchewan (currently in Regina and Saskatoon)
Artistic Swim Events & Camps (taken from Saskatchewan Artistic Swimming website)
- 7-8 events/year (held in Regina, Saskatoon and Prince Albert)
The firm acts as the City’s representative and advocate by: Managing the overall schedule, budget, and risks Project managers work only for the City—not for builders or designers. Their role is to:
Coordinating designers, contractors, and consultants
Reviewing costs and change requests
Ensuring work meets safety and quality standards
Reporting clearly to City Administration and Council.